When I left for the boat show last Tuesday, I saw one float anchored in Reynolds east of the loop bridge.

By Monday morning there was 1000 feet of floating pipe,half a dozen extra pipe floats, a pair of barges,2 tugs and a crew boat.
The barge with the crane is now at Short Beach. I think the CG station gets done first, then the inlet.
The tug captains say it's about a 3 month job once set up. Expect to see a big change
 
See less See more
2
#27 ·
weahter

LobsterD wrote:
Rick,I think the the forcast leads to their call to move the gear out of the surf zone, dont't you think??:confused:


yes Dick I agree 100% they called for it to blow last night but seems to have staled a bit and cut iback to 3 to 5's befor eit was 4 to 7 but it was a bit late
In the morning when we left 5am they were working all night when we came back around 5pm they were moved inside the turn
 